APS were contracted to provide a solution and to manage the tie in of the new connections. Following a full site survey and inspection APS manufactured the bespoke hot tap fittings to suit the 18”host pipeline with the required size outlet (16” PN16).
Attending site APS supplied and welded the four bespoke fittings to the existing host pipeline, supplied and fitted new isolation valves to each of the under pressure tees. Following the valve installation each connection underwent a pressure test for 30 minutes to prove the integrity of the new connections before the drilling process could progress. Each test was witnessed and recorded by the client. Once the pressure test were approved the connections could be drilled to make them live. APS was able to deliver the project on time and to budget to meet the client and site owners requirements.