Allied Pipefreezing Services Ltd attended site and surveyed the site and discussed options with the client.
Our line stopping option, with a temporary bypass, was decided upon as the best course of action in this scenario, as this would allow local isolation of the existing system to allow the installation of new inline valves and tees whilst still allowing the rest of the site to continue with its operations.
Double position Line stopping and bypass works were carried out on the following systems
Allied were also asked to supply and install the new inline isolation valves and tee sections to allow the new mains to be connected up before the redundant pipework was removed.
As part of the project Allied carried out the following tasks to ensure that everything went smoothly.
Tasks Involved
Conclusion
Working closely with the main contractor and scheduling works around the Arenas bookings works onsite posed a significant challenge. The majority of the works were completed out of hours on nights and between shows.
The whole project was completed within budget and on-time. Allowing for the main steel and concrete infrastructure to be installed.